The
Orphanage Budget
|
| |
|
|
| Quantity |
Price by
Square Meter |
Total
|
| |
|
|
| 350
m2 to Level the earth for Construction |
C
$30.00 por m2 |
C$
10,500.00
|
| 666.70
m2 of Walls |
C
$ 350 m2 material/labor |
C$
233,345.00
|
| 325
m2 of Roof Structure |
C$
250 m2 beam and zinc |
C$
81,250.00
|
| 288
m2 Tile Floor |
C$
220 material/labor |
C$
63,360.00
|
| 288
m 2, plychem Ceiling |
C$
185 m2 material/labor (installation) |
C$
53,280.00
|
| 13
Units of Doors |
C$
1,500.00 each door |
C$
19,500.00
|
| 13
units of Windows |
C$
900.00 each window |
C$
11,700.00
|
| 4
Units of Bathrooms Tile and Toilets |
C$
6,500.00 each bathroom |
C$
26,000.00
|
| The
Electric System 20 Units |
C$
850.00 each instalation |
C$
17,010.00
|
| Paint
2,000 m2 |
C$
20.00 per m2 |
C$
40,000.00
|
| Kitchen
14 M2 |
1,200
mt. for Gabinet, Pantry, etc. |
C$
25,200.00
|
| TOTAL |
|
C$
570,645.00
|
| |
|
|
| TOTAL (U.S. DOLLARS) |
|
$37,542.43
|
| |
|
|
| |
|
|
| Consideration:
The Roof is contemplated to be of galvanized Zinc and the cieling would be |
|
madeout of red wood and plychem. |
| |
|
|
| |
|
|
|