LosNinosDelRey > Children's Home > Budget

LosNinosDelRey.org - Children's Home

 

The Orphanage Budget
     
Quantity Price by Square Meter
Total 
     
350 m2 to Level the earth for Construction C $30.00 por m2
C$ 10,500.00
666.70 m2 of Walls  C $ 350 m2 material/labor
C$ 233,345.00
325 m2 of Roof Structure C$ 250 m2 beam and zinc
C$ 81,250.00
288 m2 Tile Floor C$ 220 material/labor
C$ 63,360.00
288 m 2, plychem Ceiling C$ 185 m2 material/labor (installation)
C$ 53,280.00
13 Units of Doors C$ 1,500.00 each door
C$ 19,500.00
13 units of Windows C$ 900.00 each window
C$ 11,700.00
4 Units of Bathrooms Tile and Toilets C$ 6,500.00 each bathroom
C$ 26,000.00
The Electric System 20 Units C$ 850.00 each instalation 
C$ 17,010.00
Paint  2,000 m2 C$ 20.00 per m2
C$ 40,000.00
Kitchen 14 M2 1,200 mt. for Gabinet, Pantry, etc.
C$ 25,200.00
TOTAL  
C$ 570,645.00
   
TOTAL (U.S. DOLLARS)  
$37,542.43
     
     
Consideration: The Roof is contemplated to be of galvanized Zinc and the cieling would be
madeout of red wood and plychem. 
     
     